Accrual Classification Process
After a purchase order item is selected, the system follows a two-step process to determine and classify accruals:
1. Initial Assessment – The system first evaluates whether accruals will likely be required for the purchase order item.
2. Accrual Classification – In the second step, the system classifies the purchase order item based on accrual requirements.
Key Determinations in Accrual Classification:
· The classification dictates the algorithm used to calculate accruals for each period.
· The system also establishes the lifetime of the purchase order, defining a start date and end date—accruals are calculated within this timeframe.
· The accrual item types and accrual methods are determined by:
o The accrual classification
1. Default Accrual Classifications for Purchase Order Items
The system provides two predefined accrual classifications for purchase order items:
· SDELS – Lifetime dates derived from the delivery schedule
· SPERP – Lifetime dates derived from the performance period
These values are part of the SAP standard delivery and cannot be modified by customers.
For further details, refer to the IMG activity Define Purchase Order Item Accrual Classifications (view V_TPOAC_ACRCLASS).
SPERP
Classification Value SPERP The system uses the classification value SPERP for purchase order items that represent either a Lean Service or an Enhanced Limit.
Lean Services For Lean Services, the Product Type Group of the purchase order item is set to 2. In such cases, users can manually enter a start date and end date in the purchase order item (via transaction ME22N). These dates define the period during which the service is expected to be received from the supplier.
Cost Calculation for SPERP Items If a purchase order item is classified as SPERP, the system (using default customizing) will calculate the planned costs by linearizing the total amount of the purchase order item across the specified start and end dates.
o The purchase order type
o The purchase order item category
SDELS
Classification Value SDELS The system uses SDELS as the default classification value for purchase order items.
Exceptions to Default Classification A different classification value is applied only if:
· The purchase order item involves the procurement of a Lean Service, or
· The BAdI method IF_BADI_POAC_MMPO_2_ACE_TRANSF->DET_POITEM_ACCR_CLASSIFICATION returns a custom classification value (e.g., Z001 or Z002).
Planned Cost Calculation for SDELS Classification If a purchase order item is classified as SDELS, the system (using default customizing) calculates planned costs by evaluating the delivery dates in the purchase order item’s delivery schedule. The planned costs for each delivery date are determined based on:
· The quantity of the delivery schedule entry, and
· The net price specified in the purchase order item.
2. Customer-Defined Purchase Order Item Accrual Classifications
Potential Use Cases Beyond Predefined Accrual Classifications
There may be scenarios where the predefined accrual classifications (SDELS and SPERP) do not meet specific business requirements.
Example: Accruals may need to be calculated using linearization between a start and end date, even when the purchase order item does not represent a Lean Service. In such cases, the system lacks predefined logic to determine the applicable start and end dates. Instead, the start date must be derived from a custom field (e.g., ZSTART_DATE in the purchase order item table EKPO).
Implementation Considerations: To support this custom accrual logic, several extension activities are required.
See note 2888110 for more details.
Customizing Accrual Item Types and Methods for MM Purchase Order Items
Objective: Define accrual item types and methods based on PO item attributes to ensure proper accrual calculation.
Steps:
1. Navigate to the Customizing Activity:
o Path: Define Accrual Item Types and Methods for MM Purchase Order Items → Define accrual item type and method based on PO item.
2. Create Entries for Relevant Combinations:
o For each applicable combination of:
§ Purchasing Document Type
§ Item Category
Z0001)
o Specify the following:
§ Accrual Item Types (e.g., accrual, planned costs, actual costs)
§ Accrual Methods (to be used for accrual calculation)
3. System Behavior:
o When an accrual subobject is created for a PO item matching the defined combination (Document Type + Item Category + Accrual Classification), the system will automatically apply the configured accrual item types and methods.
Note:
· The accrual classification is determined by the BAdI BADI_POAC_MMPO_2_ACE_TRANSFER
Source link