Bare Minimum End-to-End Master Data Setup for a Su…

  • By Sanjay
  • 10/06/2026
  • 29 Views


Material Requirements Planning (MRP) is the backbone of production planning in SAP S/4HANA. A successful MRP run depends on having the correct master data in place.

This blog provides a practical, no-nonsense guide to the absolute minimum master data setup required to execute a successful multi-level MRP run.

The scenario: Raw Materials → Semi-Finished Good → Finished Good, planned via MRP with results visible in MD04.

Before you start, understand the sequence. Each step depends on the previous one:

Image.png

Tip (S/4HANA Public Cloud): The transaction codes listed throughout this blog (e.g., MM01, CS01, CR01, CA01, C223) are not accessible via SAP GUI in S/4HANA Public Cloud. You can find the corresponding Fiori apps by searching for the transaction code directly in the Fiori Launchpad search bar. For example, searching MM01 returns the Manage Materials app.

Important: Copying a material in MM01 does NOT copy its BOM, Routing, or Production Version. You must create these separately for each material.

Transaction: MM01 (Create) | MM02 (Change)

You need three types of materials. Select the following views when creating:

  • Raw Material: Basic Data + MRP Data
  • Semi-Finished: Basic Data + MRP Data + Work Scheduling
  • Finished Good: Basic Data + MRP Data + Work Scheduling

Tip: MM01 is technically ‘create material views'. If you forgot to create a view, go back to MM01 (not MM02) and select the missing view – it will create it for the existing material.

3.1 Minimum Fields

Basic Data

Field

Value

Base Unit of Measure

PC (Pieces) – or appropriate UoM

Material Group

Your Material Group (e.g., L002 – Raw Materials, L004 – Finished Goods, L003 – Semi Finished)

MRP Header Fields

Field

Value

Plant

Your Plant (e.g. 1010)

Storage Location

Your storage location ( e.g. 101A – Finished Goods, 101B – Semi Finished, 101C – Raw Material )

 MRP 1

Field

Value

Why

Base Unit of Measure

PC (Pieces) – or appropriate UoM

 

MRP Type

PD

Enables MRP planning for this material

Lot Sizing Procedure

EX (Exact)

Lot-for-lot planning

MRP Controller

Your MRP Controller (e.g., 001)

Determines the person or team responsible for the availability of the material.

Purchasing Group

Your Purchasing Group (for e.g., 001)

Represents a specific buyer or a group of buyers responsible for procuring the material.

MRP 2

Field

Value

Why

Procurement Type

F (External)
E (In-House Production)
X (Both Procurement Types)

Raw materials are always purchased, never produced. Hence, use F (External) for Raw materials.

Planned Delivery Time

1 (day)

Rough lead time for procurement

Production Storage Location

Your storage location

Where procured material is stored

In-house production time

1 (day)

Approximate time in days that is required for a material that is to be produced in-house. Valid for Semi-Finished and Finished Goods Materials.

MRP 3

Field

Value

Why

Period Indicator

M (Months)

Planning period granularity

Strategy Group

10 (Make-to-Stock)

Production goes into shared stock

MRP 4

Nothing to maintain. Just navigate through the tab so it gets created.

3.2 Semi-Finished Good – Minimum Fields

Same as Raw Material PLUS the following differences:

MRP 2 – Key Difference

Field

Value

Why

Procurement Type

E (In-house production)

We produce this material ourselves

In-house Production Time

1 (day)

Rough production lead time (independent of quantity)

Planned Delivery Time

1 (day)

Overall time to procure/produce

Production Storage Location

Your storage location

Where produced material goes

Work Scheduling

Must be created (navigate to the tab) but no fields are mandatory to fill. Without this view, you cannot use production orders.

Note on In-house Production Time: This is only for MRP rough planning. It does NOT determine actual operation durations – that comes from the Routing. It's also independent of quantity (whether you produce 1 or 100, MRP uses the same rough lead time).

3.3 Finished Good – Minimum Fields

Identical to Semi-Finished Good. Same views, same fields, same values. Procurement Type = E (In-house production).

Transaction: CS01 (Create) | CS02 (Change) | CS03 (Display)

The BOM lists which components are needed to produce one unit of your Semi-Finished and Finished Goods material. Create a BOM for each Semi-Finished and Finished Good.

4.1 Header Fields

Field

Value

Material

Your semi-finished or Finished Good

Plant

Your plant (e.g., 1010)

BOM Usage

1 (Production)

4.2 Item List – Minimum Fields

Field

Value

Component

Material number of the component

Quantity

How many needed per 1 unit of header material

UoM

PC (Pieces)

Item Category

L (Stock item)

Image.png

To produce 1 Finished Goods material ZKU_FG_N1, you need 1 PC of Semi-Finished material ZKU_SEMI_N1 and Semi-Finished material ZKU_SEMI_N2.

Image.pngTo produce 1 Semi-Finished material ZKU_SEMI_N1, you need 1 PC of Raw Material ZKU_RAW_N1.

To produce 1 Semi-Finished material ZKU_SEMI_N2, you need 1 PC of Raw Material ZKU_RAW_N2. (Screenshot not shown)

Transaction: CR01 (Create) | CR02 (Change) | CR03 (Display)

The Work Center defines WHERE production happens and determines operation durations via scheduling formulas.

Tip: If a work center already exists, copy it when creating a new one – it saves significant effort.

5.1 Basic Data

Field

Value

Work Center Category

Machine (0001)

Standard Value Key

SAP1 – defines parameters: Setup, Machine, Labor

Image.png

5.2 Capacities – Key Fields

Field

Value

Notes

Factory Calendar

Your factory calendar

Determines working days

Start Time

07:00

When work center starts operating

Finish Time

16:00

When work center stops operating

Capacity Utilization %

100

Percentage of time that is productive

No. of Individual Capacities

1

How many parallel machines

Relevant to Scheduling

Checked

Must be checked for scheduling to work

Image.png
Click on the Capacity button.

Image.png

5.3 Scheduling Formulas

The formulas determine how operation duration is calculated from the standard values in the Routing:

  • Setup Duration = Setup Time (from routing)
  • Processing Duration = Machine Time × Quantity

These are typically pre-configured (SAP006 or similar). Just ensure they exist – they are maintained on the Scheduling tab.

Image.png

Click on the Intervals button.

Image.png

Go back and click on Intervals and Shifts.

Image.png

Transaction: CA01 (Create) | CA02 (Change) | CA03 (Display)

The Routing defines HOW production happens – which steps, on which work centers, and how long each step takes.

6.1 Header – Minimum Fields

Field

Value

Notes

Usage

1 (Production)

 

Overall Status

4 (Released)

MUST be 4, otherwise MRP won't use it

Lot Size From

1

 

Lot Size To

99999999

Maximum possible lot size

Image.png

Click on the Operations button.

6.2 Operations – Minimum Fields

Field

Value

Notes

Work Center

Your work center

Where this operation runs

Control Key

PP01 or YBP1

Depends on system customizing; must enable scheduling

Machine Time

e.g., 10 MIN

Time per piece (multiplied by quantity)

Labor Time

Same as Machine Time

Set equal to machine time for simplicity

How duration is calculated: Setup Time + (Machine Time × Quantity). Example: If Machine Time = 10 min and you produce 6 pieces, the operation takes 60 minutes.

Image.png

Tip: Double-click the operation number to open details view – it's much easier to maintain standard values there than in the table. Avoid multiple scheduled operations on the same work center. The scheduling APIs don't handle this well. If you need multiple steps, use different work centers.

Transaction: C223

The Production Version is the LINK between your material, its BOM, and its Routing. Without it, MRP doesn't know how to produce the material.

7.1 Minimum Fields

Field

Value

Notes

Production Version Name

e.g., DEF1

Per material; system takes alphabetically first by default

Lock

Not locked

 

Lot Size Min

1

Must match routing lot sizes

Lot Size Max

99999999

Must match routing lot sizes

Valid From

Today's date

 

Valid To

31.12.9999

Latest possible date

Task List Type

Routing

Select via F4 help → search by material

Task List Group/Counter

Use F4 help

Search by material to find the routing

BOM Alternative

Use F4 help

Select the BOM you created

Production Line

Your main work center

Required by SAP Cloud apps even for discrete manufacturing

7.2 Verification

After filling all fields, click ‘Check'. You should see:

  • Green traffic light for Task List – Routing exists and is valid
  • Green traffic light for BOM – BOM exists and is valid

Then: Save Changes & Close Screen → Save in the main transaction.

Image.png

Image.png

Image.pngImportant: Lot sizes in the Production Version MUST match the lot sizes in the Routing. If they don't match, the system may fail to find the connection.

Transaction: VA01 (Create Sales Order)

Before running MRP, you need to create demand for your Finished Goods Material. There are multiple ways to create demand, for example: Planned Independent Requirements (PIRs), Sales Order, or by simply creating a planned order.  

App: Schedule MRP Runs (Fiori) or Background Job with template ‘Requirements Planning MRP'

In S/4HANA Cloud, the classic MD01/MD02 transactions may not be available. Instead, use the ‘Schedule MRP Runs' Fiori app to create a background job.

 

9.1 MRP Run Parameters

Parameter

Value

Notes

Job Template

Requirements Planning MRP

 

Recurrence

Single Run / Start Immediately

 

Material

Your finished good

Multi-level run will plan lower levels too

Plant

Your plant

 

Scheduling

2 (Lead time + Capacity scheduling)

CRITICAL: Without this, planned orders have no scheduling tab and no capacity requirements

Planning Mode

3 (Delete and recreate)

Clean slate for testing; use other modes in production

Image.png

Transaction: MD04 (Stock/Requirements List)

MD04 is your primary tool to verify MRP results. Enter a material and plant to see its complete supply/demand picture.

The MRP run will create demand (sales order) and supply elements (planned orders and purchase requisitions) in the system to fulfil the demand created for your finished goods material.

Image.png

Image.png

Image.png

Image.png

Image.png

With the above bare minimum steps, you can achieve a complete multi-level MRP run in SAP S/4HANA. Start simple with one finished good, one semi-finished, and two raw materials. Once this works, expand to more complex multi-level trees.