In SAP Logistics Management, transportation planning and warehouse execution are two sides of the same medal. A shipment cannot leave without the warehouse having picked and staged the goods – and the warehouse cannot start without transportation planning having done its part first(of course, depending on the process you are in). The two disciplines are deeply intertwined: transportation planning determines the carrier and the departure schedule, warehouse execution makes the goods physically ready, and the two services exchange precise signals at every milestone that matters.
This post walks through those signals – per Shipping Process. For each process: what triggers warehouse start, when the Pickup/Delivery Document (PDD) gets linked, and what happens at Staging Completed when the warehouse processing is completed.
LTL (Less-Than-Truckload)
Warehouse start is triggered as soon as the carrier is determined on the Transportation Request – no carrier confirmation is needed. If consolidation is used, the Consignment consolidation must also be finalized first followed by the carrier determination for the consignment. Once the carrier is determined, the items are ready for warehouse processing and handed over.
At Staging Completed:
If packing into Handling Units was done (which may be enforced by the HU mandatory setting in the processing variant), Staging Completed triggers creation of Package Transportation Requests from the HU structure, which adds the HU level for the TR and consignment(in case of consolidation scenarios, where the consignment is created already).
The PDD is not yet linked when warehouse work begins. At Staging Completed, the system searches for an open PDD matching the carrier, shipping point, and planned departure time and links it to the TR. If no match is found, the TR enters an error state requiring manual resolution (see the dedicated post on TR-PDD linking timing).
Direct LTL
The bar is higher: the carrier must actively confirm the Consignment before the warehouse can start. That confirmation also triggers the creation of the PDD based on the carrier confirmation, which is linked to the TR immediately. This means the warehouse knows the carrier and planned departure from the very first step.
At Staging Completed, if packing was required, Package Transportation Requests are created from the HU structure which also updates the consignment and PDD items are also updated to package level. Because the PDD already exists, no search is needed – the update is direct.
FTL (Full Truck Load)
The subcontracting document in FTL is a Freight Order, not a Consignment. Once the Freight Order is confirmed by the carrier, the included Transportation Requests are released for warehouse processing and planned PDDs are created. The pattern is otherwise identical to Direct LTL: the PDD is known before the warehouse starts, and Staging Completed updates it to package level if packing was done.
Parcel
Like LTL, warehouse start only requires carrier determination on the TR – no Consignment exists yet. The warehouse picks and packs the goods (packing is always mandatory for Parcel). The pivotal moment is Print Label in the packing work center: this triggers Consignment creation, carrier subcontracting, and PDD creation and assignment – all in one step, before the goods reach the staging area. At Staging Completed, Package Transportation Requests are created from the HU structure and PDD items are updated to package level.
No Shipping / Customer Self-Pickup
There is no carrier, no Consignment, and no PDD. The Transportation Request is set to “Ready for Warehouse Processing” immediately on creation – no prerequisite at all. The warehouse picks and stages, and the process ends when Staging Completed is confirmed. Transportation planning receives the signal and closes out its side; no loading or carrier handoff follows.
What Staging Completed Always Does
Regardless of Shipping Process, Staging Completed is a firm boundary. Once confirmed, the HU information is final. If a correction is needed – a repack, a quantity change – staging must be explicitly reversed first. The reversal undoes everything Staging Completed triggered: Package TRs are deleted, PDD items revert to product level, and TR statuses step back. Only then can the warehouse re-work and re-confirm.
This is by design: Staging Completed is meant to be a clean, unambiguous signal that transportation can act on with confidence.
Source link